Modification No. 4 Rosemont Copper Company MOU

11/14/2009

FS Agreement No. 08-MU-11030510-010

 

MODIFICATION NO. 04

to

AGREEMENT NO. 08-MU-11030510-010

between

USDA fOREST SERVICE,
CORONADO NATIONAL FOREST

and

ROSEMONT COPPER COMPANY

 

  1. Purpose of the Modification:  The purpose of this modification is to update Attachment 2, EIS Timeline dated September 25, 2008.
  2. Change in Performance Period:  None.
  3. Change in Funds Abailable:  Not applicable.

This modification is issued pursuant to Clause No. F. 15 and Attactment 2.

Attachment 2 of the MOU is replaced with the attached revised timeline.

Except as provided herein, all terms and conditions of the referenced document remain unchanged and in full force.

Rosemont Copper Company USDA Forest Service
       
       

11/14/09
11/19/09
GIL CLAUSEN Date JEANINE A. DERBY Date
President and CEO   Forest Supervisor  
       
       
    The authority and format of this instrument has been reviewed and approved for signature:
   
11/19/09
    NORENE NORRIS DATE
    Grants & Agreements Specialist  

 

ATTACHMENT 2

EIS Timeline

Rosemont Copper Project

Notes:

  1. Timeline is contingent upon Proponent provision of necessary data/information.
  2. Timeline is contingent upon the absence of unavoidable adverse unforeseen events (e.g., complex wildfire on Forest, serious injury or illness of key player, etc.).
  3. Time line contingent upon Proponent's support of SWCA to meet the needs of the Forest for analysis
  4. Forest Service will adjust its analysis approach to imporve efficiency where possible.
Task 2010 Accomplishment
Internal review of DEIS. 1st quarter
(January - March)
Publish Notice of Abailabliity and 90-day comment period in Federal Register. April 2010
Hold public meetings, hearings, and accept public comments 2nd quarter
(April - June)
Comment analysis, FEIS supplemented or revised to incorporate comments.  Internal review completed. 3rd quarter
(July-September)
ROD issued. 4th quarter
(October - December)