Partial Backfill Alternative - January 21, 2010

 

Partial Backfill Alternative
January 21, 2010
Cooperator’s Meeting Presentation
February 3, 2010
ID Team Meeting
 
Partial Backfill Alternative
Considerations
Be responsive to an Issue
Minimize water that collects in the pit
Return waste rock to the pit
Minimize resources that are used in backfilling
Minimize air impacts
 
Partial Backfill Alternative Environmental Considerations
Compliance with all applicable regulations including ADEQ BADCT and air regulations
Maintain a Hydraulic Sink
Geochemical considerations with the addition of a mix of finer grained materials
Stormwater controls during backfill
Effect on concurrent reclamation and on reclamation planning
 
Pit Lake Development
 
Hydrogeologic Study Results
Period Pit Lake
Elevation
(ft amsl)
Pit Lake Depth
(feet)
Mine Closure (None) 0
Closure + 20 years 3,591 541
Closure + 50 years 3,751 701
Closure + 100 years 3,869 819
 
Backfill elevation – 3825 ft amsl (est.)
Elevation was estimated to maintain sink (modeling to confirm elevation estimation with operational adjustments as necessary)
 
Other Considerations
Heap Leach remains undisturbed
Haulage fleet used will be consistent in size to current fleet
Loading equipment (shovel used will be consistent with current loading equipment)
Waste rock density is 11.95 ft3/ton
Swell factor for the rock is 1.3
Amount of material necessary for backfill is 90 million tons (46 million cubic yards)
Allowance of 5% added for construction of ramps for downhill haulage
Total material rehandled 94 million tons
36-months required to complete backfill
Hauls will incorporate 3 switchbacks at -10% grade at a maximum 13 mph
Backfill and Excavation Area
Excavation on 50 foot benches
Start elevation approx 5470 ft amsl
Final elevation 5200 ft amsl
Dumped into pit from 3825 ft elevation
 
Productivity by Bench
Bench
Elevation
(ft amsl)
Tonnage
(x 1,000)
Cumulative
Tonnage
(x 1,000)
Haulage
Production
(tons/hour)
5420 8,938 8,938 379
5400 18,435 27,373 387
5350 18,689 46,062 395
5300 16,277 62,338 403
5250 12,977 75,315 411
5200 8,720 84,036 419
This information was used to determine the appropriate haulage fleet for this activity matched to one shovel.
 
Required Haulage Hours and Units
Post‐Mining
Year
Rehandle
Tons
(x 1,000)
CAT 793C Truck Fleet
Operating
Hours
Units
1 28,774 74,740 16
2 28,853 72,439 16
3 26,409 64,021 15
Total 84,036 211,201 16
Modeling indicates that 16 trucks will be required in the first 19 months of the project and 15 for the remainder.
 
Support Equipment in Addition to Haulage Equipment
One Electric Shovel
One Front End Loader
One 600 HP Track Dozer (D10)
One 850 HP Track Dozer (D11)
One 500 HP Wheel Dozer
Two Graders
Two Water Trucks
   
Discussion Points/Conclusion
Hydraulic – can maintain sink with partial backfill
Economic – negative cost implications (~$90 million)
Energy/Resource Conservation – 3 additional operational years for electric and diesel use plus water for dust control
Air Quality – 3 additional years of mining fugitives
Employment – approximately 100 people for 3 years
Reclamation– concurrent reclamation of area cannot be effectively started
Visual Result – no appreciable change to overall landform (~6% of total material)
Water Quality– potential for short term flow through condition
Traffic – 3 additional years of 100 employees commuting
Biology – continued operations presence for mining
Future Mineral – sulfides at the bottom of the pit no longer accessible
Pit Reservoir for Regional Water Storage – eliminates some storage that may otherwise available